you're here: home / resources / publications / technical articles / mileto: a reference network model  
Mileto: a reference network model
 
scope development
entry data objectives
setting types of sectors
rating  
 
MILETO was developed by UNION FENOSA in order to determine an Optimal Reference Network that could reflect the reality of the market with a reasonable degree of accuracy and would therefore produce quantified costs acceptable to the Distribution Companies. This was a project for which engineering and development were executed by SOLUZIONA engineering.

Scope
The Network Model to be developed should identify and model the market rigorously, using: the physical units minimizing investment and losses, the financial assessment of Fixed Assets, and the annual value, in order to calculate the Preventive and Corrective Maintenance costs, determine and assess the Losses, determine and assess the Undistributed Energy, and to consider the Quality and Reliability that guarantee the completion of the Indices(TIEPI and NIEPI) by zones.

Furthermore, the Model should be compatible with the inventory from which it was taken (from the Electric Substations, or SSEE, of Distribution to the Injection Points of the Transport Network). An important requirement of the Model is for it to take into account the significant differential aspects, both technical and geographical, because of their influence on the model and the cost.

Development
To achieve this objective SOLUZIONA engineering has made the necessary engineering analyses and developments, which have been converted into an information tool: the Income-Producing Electric Distribution Model called MILETO which models a reference network for Low Voltage users up to High Voltage injection points.
MILETO models the network that connects and distributes energy to each and every one of them.

Entry data
The model's lower limit is based on each of the geographical coordinates and the data on contracted Capacity and annual energy consumption of all users of low, average and high voltage. The model's higher limit is set by the coordinates of the High Voltage injection points, that is, all or some of the Substations of the Transmission Network with usable capacity and necessary for Distribution.

Entry data include the library of components and installations with their assessment of materials and manpower. This is a modular library which allows enabling or disabling installations, adding and reforming. Entry data also include the Maintenance Ranges, Failure Rates, repair Times, References and service Quality indices by Zones, municipal and provincial borders, geographical elements, etc.
When the coordinates and data on the Distribution Substations and Transformation Centers are available, one can compare the modeled network with the actual one.

Objective
The objective is to establish the best possible reference frame for determining the Distribution Rate.
We can summarize the possible approaches into three:
1.- IPC-X/kWh Rate,
2.- Comparison between companies
3.- Reference network model.

When the approach is based on applying a IPC-X/kWh distributed rate, adjusting the regulator -- the efficiency factor X which is inferred from the companies' financial results, a global and general approach is being made. This does not reflect geographic nor market reality, nor the resulting network needed to maintain supplies, by legal obligation, to complete all the zonal quality indices that are to be defined.

To establish a precise comparison between companies, it is necessary that these be similar. In Spain they are not similar, neither in terms of size nor in homogeneity of the market. The third approach, which we understand to be more adequate, is to build a reference Network Model adapted to the geographical and market reality.

What should be the scope of such a Model? There are three options:
- A scope that completely models the entire Network.
- A scope which is based solely on inventory.
- A scope that combines a partial network model and inventory.

If we had a complete inventory of all the Distribution installations in their different voltage levels we would not need a model. It would not even be necessary to send signals on the rating since the theoretical rating that would be given by the real network could be calculated and gauged using the declared incidences.

The real situation is quite different, as there is no complete nor reliable inventory in BT, as there is in MT and AT where it is possible, because it deals with less volume. Producing a new and complete inventory is deemed to be a very arduous task that would not make sense. For example, gauging and auditing the RBT Subway would have a very high cost.

It is a task which the companies can undertake to gain a more thorough knowledge of their networks and to facilitate maintenance, operation etc.

In a complete scope Optimal Reference Network the reliability of the same can be questioned because of being far from the reality it attempts to replicate.

A semblance may be required in the order of magnitude of the modeled and real installations. For example the number of CCTT, of machines and the Power installed.

Let us remember that this is not about making a stylish nor academic exercise in which the volume of installations may be indifferent, but of compensating the costs derived from existing installations with a credible model adjusted using adequate signals by rating that allow the establishment of bonuses and penalties.

The measuring of the BT, and of each Transformation Center plus its RBT, is reasonably stable in time and optimal given its reduced size. Thus, a model can reproduce this situation with a good semblance to reality.

In MT the situation is quite different. The situation of each of the Substations -or SSEE- that exist is a result of reconciling available spaces, political administrative authorizations of entities from different spheres, technical needs, geographical arrangements, etc.

It could be assumed that at the time of its planning its position would be optimal; as time passes, with the load evolution, neither the number nor the location nor the individual capacity of each SE will be similar if we use these in the model.

If we model several years consecutively we will find movable SSEE which do not allow valid financial signals to be produced.

We understand that to compare a Model against the Inventory is not necessary since it is possible to reconcile both approaches.

Our proposal is to adopt a partial scope Model patterning the BT and the MT feeders to connect the Inventory Substations even at its own voltage level and starting from there with the actual network.

This presentation is algorithmically more complex than complete modeling since the model's degrees of freedom are reduced. However, a solution is achieved that is optimal for some given positions of the SSEE, guaranteeing the convergence with reality and allowing rating signals to be actually contrasted.

Setting
The essential aspect to consider in order to have a clear idea of the magnitude of the challenge is to process each and every one of the data of the BT, MT and AT users -- more than 20 million coordinates. In addition, the values of the contracted power are different for each user, being discreet values, and their distribution is given by their real position which require aspects like leakage or concentration to be treated very seriously.

Identification and Modeling of the market
With the individual information of the X,Y,Z UTM coordinates of each user the population cores are identified with parameter criteria of absolute or relative geographical proximity (density). The town structure is automatically modeled, and the actual streets and blocks are pointed out resulting in a town model similar to reality.

The structured towns generate a model defined by streets and blocks (closed premises) and the minor or not so well-defined cores appear as polylines (open premises) which join, as in reality, the current consumption with minimum distance trees.

This is the model most similar to the actual current consumption since it is generated from them, and it is updated, doing away with errors due to homes without electricity, etc. It is also the most economical since it does not require additional information..

Alternatively the MILETO Model can work against reference maps, digitized or cadastral mappings. This alternative can be more accurate but is much more costly and presents some problems that are difficult to solve such as the different updating degree of the mapping against the homogeneity of the users' coordinates, the lack of mapping for a big number of population cores, its elaboration with various criteria that require dealing with an information systems which is slow, complex and that produces uncertain results.

Sector Types
One could define sector types of a territory, conduct an in-depth analysis, build the adequate optimal network with planning criteria and later extrapolate to the rest of the territory's sectors.

But considering the need for complete identification and modeling of the market as proposed by MILETO, this alternative presents a clear disconnection with reality, as it identifies characteristics and extrapolates them to supposedly similar sectors.

This would the produce an illicit generalization because markets are complex social, financial and geographical entities that cannot be reduced or simplified to a few model sectors.

Categorization
The population cores to be given electricity are to be categorized based on their size (clients, loads) as urban, rural and remote. This categorization, while automatic, is one of the most delicate aspects of the process as it dictates the mode of electrification.

Thus, for example, to categorize a core as remote implies utilizing the Tensioned low voltage network, Transformation Centers -CCTT- concrete transmission lines and in addition being optimized with other cores so as not to designate a CT a priori in each core such as occurs in reality.

To categorize as rural or urban also has consequences on the use of certain types of installations, even when within each group they may be inhabited or uninhabited (leaving at least one model) to have a flexible configuration.

It would appear that remote cores would be excluded from Underground installations, but for the CCTT houses or buildings will appear, as well as the laid network, the underground network, the mesh architecture, etc.

MILETO minimizes the consequences of this aprioristic rating since it supports an overlapping of types of installations which can be used in the cores located in the remote, rural and urban separation limits.

 
subscribe
to highlights
contact us send
this article
print
this article